7 February 2017 – Progress Update

Since the last update on January 20th progress has been made on the water project, building repair, and painting. Water Project By our last update on January 20th most of the pipe had been laid, and a trial run of the tap at the men's quarters was successful. Since then the pipeline has been laid … Continue reading 7 February 2017 – Progress Update

Successful Trial Run for Water Project

This update will be a brief one - we just want to share that the water is successfully running from taps outside of the men's buildings! Pictured is Budhu, the head man in charge at the village, testing it out. It's possible that watching this I was more excited than he was!! What a miraculous … Continue reading Successful Trial Run for Water Project

Leprosy Village Update – January 13, 2017

This week significant work has been done on the building which the villagers cook in. The wall pictured below was so worn that water could come through the cement that holds the bricks together. This is the condition of the wall pictured, the pillars supporting the roof, and the wall that is not pictured but … Continue reading Leprosy Village Update – January 13, 2017